S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
155. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return is observed on the surface where such return was planned;
(3)  a return of drilling fluid indicates that the cement height required for cementing is not reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1251-2018, s. 155.
In force: 2018-09-20
155. The authorization holder must submit to the Minister, for approval, the corrective actions to be taken where any of the following situations occurs:
(1)  a cementing operation provided for in the technical program cannot be carried out;
(2)  no cement return is observed on the surface where such return was planned;
(3)  a return of drilling fluid indicates that the cement height required for cementing is not reached;
(4)  there is uncertainty as to reaching the cementing goals.
O.C. 1251-2018, s. 155.